How much concrete do I need?

Concrete is ordered by volume, so the core job is to turn the dimensions of the space into cubic metres. This guide shows the calculation transparently and explains where an allowance may be sensible.

Reviewed: 20 September 2026 · How we check calculations

The core calculation

For a rectangular pour, multiply length by width by depth, with every dimension expressed in metres. A 4 m × 3 m slab at 100 mm deep uses a depth of 0.10 m: 4 × 3 × 0.10 = 1.20 m³.

That is the geometric volume. It does not automatically account for uneven excavation, spillage or a base that is slightly deeper than measured. BuildCalcs therefore keeps the measured quantity and any allowance conceptually separate.

Concrete volume by area and depth

Area75 mm100 mm125 mm150 mm
5 m²0.38 m³0.50 m³0.62 m³0.75 m³
10 m²0.75 m³1.00 m³1.25 m³1.50 m³
15 m²1.12 m³1.50 m³1.88 m³2.25 m³
20 m²1.50 m³2.00 m³2.50 m³3.00 m³
25 m²1.88 m³2.50 m³3.12 m³3.75 m³
30 m²2.25 m³3.00 m³3.75 m³4.50 m³

These values are calculated directly from area × depth. They are reference quantities, not supplier pack or delivery sizes.

Worked project examples

Small shed base

A 3.0 m × 2.4 m base at 100 mm: 3.0 × 2.4 × 0.10 = 0.72 m³. A 10% planning allowance would make 0.792 m³, normally shown as 0.79 m³ before considering how a supplier sells the material.

Garden path

A 9 m path, 0.9 m wide and 75 mm deep: 9 × 0.9 × 0.075 = 0.6075 m³, or 0.61 m³ to two decimals.

Garage-sized slab example

A 6 m × 3 m area at 125 mm: 6 × 3 × 0.125 = 2.25 m³.

Why measured depth matters

Depth has a direct linear effect on volume. Increasing a 100 mm slab to 125 mm increases the concrete volume by 25%. Measure at several points if the excavation is irregular rather than assuming the neat design depth is what exists on the ground.

Allowance is not the same as the calculation

An allowance is a planning decision, not part of the volume formula. Keeping it visible lets you compare the exact geometric quantity with the quantity you may choose to order. Avoid adding an allowance twice—for example once in your dimensions and again as a percentage.

Common errors

Calculate your own project

Enter your actual measurements rather than relying on a generic example.

Open the Concrete Calculator →